Below is a list of news items for the City of Moorhead with the most recent items at the top.  If you would like to see news for a certain category, you can select it from the the drop-down box labeled (All Categories).  Any news older than 90 days is automatically archived and removed from this list.

You can also subscribe to our eNotifications to automatically receive emails as we post news to the site.

SE Main|20 St|21 St Underpass Project Update

Post Date:06/01/2020 8:00 am

The SE Main|20 St|21 St Underpass project is approximately 70% complete (underpass construction, track, and signal work). It was announced last summer that slope stability issues associated with temporary shoring systems were causing delays in constructing the retaining walls needed to support the permanent railroad tracks as they approach the bridges. The temporary shoring systems needed to install the permanent improvements have been redesigned, and work that was put on hold until this was completed will restart in early June. Unfortunately, the redesign took significant time and negatively impacted the construction schedule. The project will not be open to traffic in 2020.

During the period in which work on the retaining walls was delayed, progress continued on other areas - particularly road construction around the tie-in points of the underpass project, and portions of the three bridges. Approximately 65% of the total excavation has been completed.

What remains to be done?

  • Retaining walls and bridges: Two retaining walls must be completed before the two north bridges can be completed. Construction of these walls will likely start up again in early June. One of the walls and the two north bridges may be completed by mid-summer, but construction of the other wall will last into September 2020.
  • Permanent Railroad Tracks: The permanent OTVR track, the last remaining bridge and the permanent BNSF track must be completed after the aforementioned steps. The revised schedule anticipates late November / early December of 2020 for these elements.
  • Excavation, storm sewer, and road construction: The remaining excavation, storm sewer and road construction to complete the underpass must occur after the permanent track is in place and weather permits. The construction of these final elements will resume in spring 2021.

Every effort is being made to complete the project as early as possible. However, the safety and integrity of the permanent infrastructure (walls, bridges, etc.) and keeping the project within the approved budget will continue to be top priorities. The complexity of resolving the issues encountered has resulted in a delay in opening until the summer of 2021.

Project Contact: Tom Trowbridge, Assistant City Engineer, 218.299.5390