Below is a list of news items for the City of Moorhead with the most recent items at the top.  If you would like to see news for a certain category, you can select it from the the drop-down box labeled (All Categories).  Any news older than 90 days is automatically archived and removed from this list.

You can also subscribe to our eNotifications to automatically receive emails as we post news to the site.

Construction Update: SE Main|20 St|21 St Underpass Project

Post Date:04/28/2022 1:27 pm

As of April 27, 2022, the project is approximately 90 percent complete. 

  • Both the BNSF and OTVR railroad tracks are completed and operational.
  • Approximately 85% of excavation has been completed (204,000 cubic yards).
  • Approximately 90,000 feet of structural support piling (98% of total contract amount) has been installed.

Upcoming Milestones:

  • Finish storm sewer installation (early May)
  • Complete remaining piling (approximately mid-May)
  • Finish retaining walls (end of May/beginning of June)
  • Concrete paving, curb & gutter, medians and sidewalks from late May through early July
  • Complete underpass and open to traffic; anticipated mid-July 2022
  • Complete BNSF wye track and close 1 Ave S to through traffic; anticipated July-August 2022

 

20-21 Update April 2022