Project Vital Statistics as of April 27, 2022
Total Contract Work Completed: 90%
- Both the BNSF and OTVR railroad tracks are completed and operational.
- Approximately 85% of excavation has been completed (204,000 cubic yards).
- Approximately 90,000 feet of structural support piling (95% of total contract amount) has been installed.
Upcoming Milestones
- Finish storm sewer installation (early May)
- Complete remaining piling (approximately mid-May)
- Finish retaining walls (end of May/beginning of June)
- Concrete paving, curbs/gutters, medians and sidewalks (late May through early July)
- Complete underpass and open to traffic; anticipated mid-July 2022
- Complete BNSF wye track and close 1 Ave S to through traffic; anticipated July-August 2022
Major Road Closure/Detour Continues:
Traffic should use either 1 Ave S, 12 Ave S, or Highway 10 as an east/west route and 34 St S or 8 St S as a north/south route. Closure of the intersection of SE Main and 20 St|21 St (all directions) will remain in place, likely until June 2022.
Other Travel Impacts:
20 St from 8 Ave to 6 Ave is now open, however, 20 St north of 6 Ave remains closed
21 St S from 2 Ave S to 4 Ave S and 4 Ave S from 21 St S to 22 St S is open to traffic, one lane in each direction
Main Ave from 17 St S to 19 St S and 19 St S from Main Ave to 4 Ave S is open to traffic
Project Description
The proposed project will reconstruct and realign the intersection of SE Main Ave and 20 St/21 St to pass under new bridges that will carry the BNSF and Otter Tail Valley Railroad tracks over the streets. The project will result in improvements to safety and congestion for vehicles, bicycles, pedestrians, and emergency services.
The project also includes the construction of new track (called a wye) that will allow direct northbound to eastbound and westbound to southbound train movements. Under existing conditions, trains must travel into the Downtown area, stop, and reverse direction to make these movements. The wye will eliminate delays at the Downtown crossings associated with trains backing up. Construction of the wye will require the closure of 1 Ave S near the wye track.
Project Layout
City Contacts
Tom Trowbridge, Assistant City Engineer
General Construction Questions 218.299.5395
Jon Atkins, City Traffic Engineer
Detour and Traffic Concerns 218.299.5388
Levi Hockett, City Inspector
Specific Construction Questions 218.299.5396
For Other Inquiries
Contact the Engineering Department
Additional Information
Animated Depiction of 20th & 21st St/SE Main Avenue Grade Separation Project
20 & 21 St/SE Main Ave Grade Separation Project Layout
July 11, 2018 - Community Information Meeting - SE Main Ave 20/21st ST Railroad Grade Separation
August 12, 2021 - Underpass Open House - SE Main Ave 20/21 ST Railroad Grade Separation FAQ